Civil Work for FSF around CPF3 Project and Well Pads

    Provision of civil works for FSF around the CPF3 project area and associated well pads facilities in Halfaya.
Civil Work for FSF around CPF3 Project and Well Pads

Project Overview

Execution of comprehensive civil infrastructure works for oilfield development at Halfaya Oilfield, including construction of access roads and well pads to support drilling and production operations.

The scope encompassed site clearance, bulk earthworks, cut and fill, grading, compaction, pavement layers, asphalt surfacing, drainage systems, reinforced concrete works, utility crossings, traffic control measures, and final commissioning of the infrastructure.

The project was delivered in full compliance with PetroChina technical specifications, international engineering standards, and stringent HSE requirements, ensuring durable infrastructure and uninterrupted field operations.